Project Type: Transformation
This project transformed an existing desulfurization wastewater treatment system to improve efficiency and reduce costs.
![latest company case about [#aname#]](//www.huadeep.com/images/load_icon.gif)
Process Flow:
- Desulfurization wastewater is pumped into a high-efficiency reactor.
- Simultaneously, an integrated high-efficiency water purification agent is precisely fed into the reactor using a dry powder dosing machine.
- A high-speed mixer ensures thorough mixing of the agent and wastewater, promoting the formation of large flocs.
- The well-mixed wastewater is pumped into high-efficiency cyclone clarifiers for further flocculation, precipitation, and clarification.
- Concentrated sludge settles at the bottom of the clarifiers and is fed, along with the underflow from the gypsum cyclone, to a disc dewatering machine for dehydration.
- Treated clean water overflows from the clarifiers and is collected in a clean water tank for reuse.
Equipment Features and Advantages:
- Simple process with minimal equipment: The system primarily uses 1 high-efficiency reactor, 2 high-efficiency cyclone clarifiers, 2 wastewater lifting pumps, and 2 sludge transfer pumps.
- Highly automated and easy to operate: The system can be started and stopped with a single button, minimizing operator intervention.
- Compact footprint and low civil construction costs: The entire system occupies less than 30 square meters, reducing infrastructure needs.
- Low operating cost: The system requires only one chemical, resulting in a treatment cost of 3-4 yuan per ton of water.
- Stable operation and excellent water quality: The system ensures consistent performance and effluent that meets regulatory discharge standards.
Customer Pain Points Addressed:
- Reduced operating costs
- Enhanced system stability
- Lowered workload for operators (compared to the complex, labor-intensive operation of the previous system)
- Consistent water discharge quality meeting regulatory standards
Applicable Industries:
- Coal-fired power plants
- Aluminum plants
- And other industries with desulfurization wastewater treatment needs
![latest company case about [#aname#]](//www.huadeep.com/images/load_icon.gif)
Core Components and Warranty:
Core components: High-efficiency reactor, High-efficiency cyclone clarifier
Warranty period: 1 year after equipment acceptance
Product Specifications:
High-efficiency reactor: Diameter 2.5 meters x Height 3.0 meters, Net weight 5 tons
High-efficiency cyclone clarifier: Diameter 3.0 meters x Height 6.4 meters, Net weight 8 tons
Additional Information:
Total operating power: 17.37 kW
Productivity: 30 tons per hour
This case study demonstrates how the Jiahu Bay Desulfurization Wastewater Treatment Project successfully addressed critical challenges in an existing wastewater treatment system. The transformed system offers a simplified, cost-effective, and reliable solution for various industries.